After a government meeting, you and the State Programme Manager agree five follow-up actions involving...
After a government meeting, you and the State Programme Manager agree five follow-up actions involving different team members. What is the best way to make sure these actions are completed?
1. Ask each person to note their own action, and check what has been done at the next government meeting.
2. Record each action with an owner and a deadline, share it, and check progress until all are done.
3. Send the team a reminder email before the next meeting.
1. Ask each person to note their own action, and check what has been done at the next government meeting.
2. Record each action with an owner and a deadline, share it, and check progress until all are done.
3. Send the team a reminder email before the next meeting.

info@snapandsolve.com